Observatory

Planning fallacy: estimating project time and costs

· Zeloni Corporation

“This time we have everything under control.” It is an understandable sentence at the start of a project. We have learned from past delays, chosen new tools, prepared a better schedule. And yet the estimate can still be too optimistic. The problem is often the point from which we look at the work: we imagine how it should go, and give little weight to how similar projects actually went. That is the planning fallacy, and it concerns costs as much as time.

As always in this Observatory, we keep three things apart: what the research shows, what we observed in our own companies, and what we propose. It is the reader’s pact of the Mental Sciences Applied to Business.

What the planning fallacy is

The expression planning fallacy comes from work by Daniel Kahneman and Amos Tversky in the late 1970s. It describes the tendency to underestimate the time and costs of a project even when we know that similar projects took longer. According to the authors it comes from forecasting “from the inside”: we look at the plan of this one project and neglect how similar cases went.

Knowing the bias exists is not enough to avoid it. Kahneman and Tversky compared it to optical illusions, which stay convincing even when we know they are illusions.

What the research shows

In five studies with university students, Buehler, Griffin and Ross observed overly optimistic forecasts, both for academic tasks and for household chores. Without any intervention, fewer than half of the participants finished within the time they had predicted. While forecasting, they thought mostly about their plans for the task; they thought little about past delays, and explained them away as special cases unlikely to recur. In the first study, students writing their thesis expected on average to submit it in about 34 days and took about 55. Fewer than a third submitted within their own estimate, and more than half went past even the date they had given imagining that everything would go wrong.

In the same work, remembering past delays was not enough to change the forecasts. The optimism disappeared only when participants had to link those experiences explicitly to the new task. The forecasts became less optimistic on average, but not more precise, and the authors themselves wrote that they did not yet have solid evidence that recalling the past makes estimates more accurate. Other corrective techniques give mixed results: imagining negative scenarios, for example, did not improve forecasts about one’s own tasks.

Underestimation is not universal either. A review of studies on time predictions indicates that underestimation is more frequent than overestimation in engineering and management studies, but not in psychology studies. The same authors observe that short tasks are often overestimated and larger projects underestimated, while warning that part of this may be a statistical effect. There are statistical reasons why delays seem to be everywhere: projects that look quick and cheap are more readily started, a tender tends to reward the most optimistic bid, and a task can last much longer than planned but never less than zero, so overruns weigh more than savings.

Overconfidence also needs precision. It has at least three distinct forms: overestimating one’s own performance, believing oneself better than others, and being too sure of the precision of one’s beliefs. The first two can even reverse depending on how difficult the task is. The third, excessive precision, is the most persistent: we can be cautious about the result and too sure about the date on which we will reach it.

Why inside estimates can be optimistic

A hypothetical example: a company wants to open a new online shop. The schedule includes development, product upload and launch. Each activity has a credible duration. What is missing are the waits: materials delivered late, incomplete product sheets, approvals, corrections, tests. The estimate describes a process without friction, while the real project also depends on steps nobody fully controls.

Adding a generic margin can help, but it leaves the reason for the risk unclear. Kahneman and Tversky observed that a safety margin added by eye is rarely enough, because the corrected figure stays anchored to the starting estimate. A predictable supplier delay and uncertainty about demand are not the same problem either. We propose distinguishing working time, waiting time and dependencies. When a date changes, this distinction shows which part of the model was wrong.

Use comparable projects and estimate ranges

The remedy Kahneman and Tversky proposed is to look at the project “from the outside”: besides asking which steps it requires, ask how long similar projects usually took. Kahneman and Lovallo suggest comparing homogeneous units, such as the ratio between actual and planned spending. Bent Flyvbjerg turned the idea into a method for large public projects, reference class forecasting.

It is worth being clear about the evidence. Kahneman and Tversky presented their procedure as a suggestion for practice, not yet systematically evaluated. The evidence that came later is encouraging but limited. One study on data from real projects found that forecasting based on similar projects was the most accurate of the methods compared. Another, on investment decisions, found that a set of similar cases guides better than a few familiar analogies.

In practice, look for a few comparable cases: your own past projects, information from partners, sector data, as long as the comparability is reasoned. A brochure website is not a good basis for estimating a catalogue integrated with management software. A project run by a dedicated team says little about one entrusted to people who also follow other work. For each case, collect the initial estimate, the actual time, the main waits and the changes in scope. Even a few cases can reveal a recurring error; they are not enough to build a precise probability.

Then prepare a range, and write down what justifies it. Ranges need care too: we tend to give ranges that are too narrow, and in the thesis study more than half of the students went past even their worst-case date. For this reason we propose deriving the high end of the range from the overruns of past cases, not only from the worst scenario we can imagine.

A worksheet for reviewing time and costs

Our proposal, with hypothetical figures for the online shop:

LineWhat to writeExample
Internal estimateThe team’s date and budget, built step by step10 weeks, €18,000
Comparable projectsThree to five past projects of the same kind, with estimate and actualThree past launches: 8 weeks became 11, 9 became 14, 12 became 15; budgets of €15,000, €20,000 and €16,000 became €17,000, €24,000 and €22,000
Past overrunsActual divided by estimated, for time and costTime from 1.25 to 1.56; cost from 1.13 to 1.38
RangeLow end: the internal estimate. High end: the estimate times the largest past overrun10 to 16 weeks; €18,000 to about €25,000
Review triggersEvents that require a new estimate, decided in advanceA supplier delay of more than a week; a change in scope; a key person unavailable
Promise to the clientThe date communicated, with the assumptions it rests on16 weeks, if materials arrive by week 2

If you choose a more ambitious deadline than the range suggests, write down which resources or decisions should make it possible. The same applies to cost: the quote for the initial work is not the project’s total requirement. Testing, maintenance, management and delays can change the exposure. Make these items visible before deciding, without inventing standard percentages.

Estimate and promise

An internal estimate organises the work. A promise to a client creates an expectation and can become an obligation. Kahneman and Lovallo noted that a forecast adopted officially often becomes a target and a commitment, and this pushes it towards optimism. In a field study and a laboratory study, people with an incentive to finish early made more optimistic forecasts; in the laboratory they looked more at their plans and less at past experience. The team should know which assumptions support a promise: availability of materials, number of revisions, response times, delivery criteria. Then a change can be discussed on its merits. How a goal turns into the actions that make it achievable is discussed in business goals.

When the estimate moves, the question is not how to defend the first figure. What has already been spent does not justify the next step (the sunk cost fallacy), and when the uncertainty is too high to estimate at all, a different logic may help: deciding how much you can afford to lose (effectuation).

A log that improves the next estimates

At the close of a project, compare forecast and result. Look for the error that repeats: approvals, people’s availability, integrations, requested changes. Record also the cases where the estimate was too high. A written log helps because memory is not reliable: according to one review, we may underestimate future durations partly because we remember past tasks as shorter, an explanation still debated. Receiving feedback on results makes estimate ranges more realistic but does not eliminate overconfidence, especially when the work is our own. And those who have studied software estimates for years advise against rewarding exact estimates or punishing optimistic ones: you get higher estimates, not necessarily more precise ones. The aim is to calibrate, not to blame.

Two questions we are often asked

Does every project delay imply a planning bias? No. Short tasks are often overestimated, and part of the delays depends on which projects get started: those that looked quick and cheap. A single delay can come from an event nobody could foresee. A bias shows up as a pattern, when the same kind of error repeats across projects, which is why the log matters.

How do you choose a useful reference class? Look for projects similar in the things that drive duration and cost: type of work, size, the team that runs it, the external dependencies. Prefer several roughly similar cases to one very familiar one, and compare homogeneous units, such as the ratio between actual and estimated time. If no comparable case exists, say so, and widen the range.

Estimating time and costs is part of Business Starter, the first of our book-courses.

Sources

Batselier, J., and Vanhoucke, M. (2016). Practical Application and Empirical Evaluation of Reference Class Forecasting for Project Management. Project Management Journal, 47(5), 36–51. https://doi.org/10.1177/875697281604700504

Buehler, R., Griffin, D., and MacDonald, H. (1997). The Role of Motivated Reasoning in Optimistic Time Predictions. Personality and Social Psychology Bulletin, 23(3), 238–247. https://doi.org/10.1177/0146167297233003

Buehler, R., Griffin, D., and Ross, M. (1994). Exploring the “planning fallacy”: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366–381. https://doi.org/10.1037/0022-3514.67.3.366

Flyvbjerg, B. (2006). From Nobel Prize to Project Management: Getting Risks Right. Project Management Journal, 37(3), 5–15. https://doi.org/10.1177/875697280603700302

Halkjelsvik, T., and Jørgensen, M. (2012). From origami to software development: A review of studies on judgment-based predictions of performance time. Psychological Bulletin, 138(2), 238–271. https://doi.org/10.1037/a0025996

Halkjelsvik, T., and Jørgensen, M. (2018). Time Predictions: Understanding and Avoiding Unrealism in Project Planning and Everyday Life. Springer. https://doi.org/10.1007/978-3-319-74953-2

Kahneman, D., and Lovallo, D. (1993). Timid Choices and Bold Forecasts: A Cognitive Perspective on Risk Taking. Management Science, 39(1), 17–31. https://doi.org/10.1287/mnsc.39.1.17

Kahneman, D., and Tversky, A. (1977). Intuitive prediction: Biases and corrective procedures. Technical Report PTR-1042-77-6, Decision Research. Published in 1979 in TIMS Studies in Management Science, 12, 313–327.

Lovallo, D., Clarke, C., and Camerer, C. (2012). Robust analogizing and the outside view: two empirical tests of case-based decision making. Strategic Management Journal, 33(5), 496–512. https://doi.org/10.1002/smj.962

Moore, D. A., and Healy, P. J. (2008). The trouble with overconfidence. Psychological Review, 115(2), 502–517. https://doi.org/10.1037/0033-295X.115.2.502

Newby-Clark, I. R., Ross, M., Buehler, R., Koehler, D. J., and Griffin, D. (2000). People focus on optimistic scenarios and disregard pessimistic scenarios while predicting task completion times. Journal of Experimental Psychology: Applied, 6(3), 171–182. https://doi.org/10.1037/1076-898X.6.3.171

Roy, M. M., Christenfeld, N. J. S., and McKenzie, C. R. M. (2005). Underestimating the Duration of Future Events: Memory Incorrectly Used or Memory Bias? Psychological Bulletin, 131(5), 738–756. https://doi.org/10.1037/0033-2909.131.5.738